I-4 LOGISTICS

I-4 Logistics Project

About This Project

With an overall schedule from mobilization to panels erected in 11 weeks. The 162 panels were erected using a 330 ton crane for panels weighing over 253,000 lbs. The pants leg panels with lids attached at the buildings NE and NW elevations provide a unique look while also constructed as tilt-up panels. All panels including ramp walls and electrical rooms were constructed as tilt-up panels.

Location

Seffner, FL


Supported Area

425,000 sq. ft. warehouse